Write a change order for work added after an estimate
The client adds a second door after the quote is signed.
Your original estimate covers one door. A second door will cost the client $180 more and add half a day. What should the written update contain?
Show the answer
The extra door, $180 and half a day, sent for approval before work.
Name what changed, state the added cost and time, and ask the client to approve the change before you start it.